by Soman
ERP implementation has entered its peak
season whereby involvement from Leopad team increased. New implementation
partner has revised the project schedule and maneuvering the project back to
the track. There will be no changes to planned ‘Go-Live’ date. New consultants
mobilized by implementation partner for Project, Human Resources and technical
support. They have started to conduct pre-study, prepare SDD and training.
Leopad project team has scheduled sessions continuously for relevant modules to
catch up the schedule.
Apart from Project and HR module, SDD
review also actively being carried out by super users. Process owners conducted
Internal reviews and inter-department discussions pertaining SDD & process
flows. Distribution module SDD was first SDD being approved by Steering
Committee (SC). The process owners with his team and other departments did
detailed discussions throughout month of September. Process owner presented the
SDD key elements to SC for approval. SC has approved Distribution SDD with some
Opportunities For Improvement (OFI) comments. Distribution SDD approval is one
of the important milestone that Leopad team has achieved. I would like to congratulate and thank all
involved in this SDD approval process.
Data gathering is one of the most integral
factors in successful ERP implementation. However, studies show that many
organizations have underestimated this task that led to the failure of
implementation. Data gathering and cleansing is important to ensure accurate
and complete master data is available for completing testing process. Without
complete master data, business process flow cannot be tested completely. Data
gathering and cleansing involves: -
- Convert data
- Collect new data
- Review all data input
- Clean-up data
Users cannot assume that 100% of the data
can be converted, as there may be outdated information in current system. Users
need to determine which information should be converted through an analysis of
current data. Users also need to identify new data need to collected and source
of the data. Implementation partner will provide a data collection template for
this purpose. Review and cleaning up data to be done by users in order to
ensure correct required data migrated to ERP environment.
Apart from data collection, many other
tasks to be done in coming months. Post ERP roles and responsibilities to be
discussed with entire Leopad management team. Application Solution Test
expected to be carried out in late October. Therefore, continuous support required
from entire team required in order to complete scheduled task on time.
Lets Make it Happen.
Wednesday, October 4, 2017
by Soman
Dear Team,
Flowchart preparation
Branch Involvement
Top Management Briefing
“Lets Make It Happen”
Dear Team,
Solution Design Documentation (SDD) started to be submitted by consultants in the month of August. Process owners started the review of SDD with their key personnel. Review team must wet through entire SDD and identify the gaps. Mainly, review team must ensure all the scenarios covered in the SDD. After completion of first level of review, Process owners will present the SDD to other relevant parties. Discussions will take place regarding the cross function areas. Process owners will present the core item to steering committee (SC) prior to the approval. SDD approval expected to be completed by end of October 2017.
Flowchart preparation
Process owners have begun to prepare their flowcharts in the month of August. Level 1 flow presented to SC and all process owners. Process owners are preparing Level 2 and 3 flows of their processes. Level 2 and 3 flow charts will be presented to core team for further detailed discussions.
Branch Involvement
As we are going to start AST, branch involvement in ERP implementation will be increasing. Data collections, sanitizations and migrating to pre-production server need to be done in order to prepare for AST & CST. Branch managers and Head of Departments are also required to define the roles of their work force post ERP implementation.
Therefore, BM’s and HOD’s will be involved in more discussions and brainstorming sessions from now onwards.
Process owners will be requesting informations such as customer and supplier details at branch level. End users are required to test these data’s during CST. As Leopad adapting digital transformation, more online meetings will be conducted which helps all relevant parties attending the meetings and also reduce travels.
Top Management Briefing
CEO has briefed the core team regularly latest updates on the project. CEO also stressed that all core team members required to allocate 80% of their time in ERP in order to ensure project completion on-time. CEO also requested fullest commitment from all parties towards successful implementation of ERP.
“Lets Make It Happen”
Friday, September 8, 2017
THE
JOURNEY CONTINUES…
by Soman
Dear Team,
Our journey
continues in the next phase of ERP implementation. Solution Design
Documentation (SDD) is the heart of the ERP. SDD includes information about the
working elements of the overall solution, including IFS standard features, gaps
and integrations. It is very important to get the entire solution depicted in a
pictorial representation.
Objectives of
the SDD
• The
details of the business flow in the future solution based on IFS and JOIN
• Solution
validation
• The
single point of reference for future value additions, issues and
troubleshooting
• Documenting
the high level
• Business
and solution flow diagrams
SDD documents
submission by the consultants expected to be completed by 18/08/17. A
walkthrough session is arranged with key users to explain SDD processing
methods. SDD reviewing and acceptance process expected to be completed by mid
of September 2017. Application Solution Testing (AST) will follow through right
after the SDD acceptance. Key users will verify their processes in the system
based on the SDD documents.
Bidding Logbook
After
several discussion, JOIN, a partner software of IFS, has developed a solution
for bidding logbook (bid log). Estimation and Proposal Department (EPD) team is
currently testing the bid log by entering live data for past one month. Both
consultant and EPD are continuously troubleshooting and upgrading the solution
before release to the key users. Solution is expected to be ready for release
in the month of September 2017. On behalf of management, highest appreciation
to EPD team contribution and continuous support in testing this solution.
Work Breakdown
Structure
We are also started to set up the
Work Breakdown Structure (WBS) for all project scopes. This process require
numerous brainstorming sessions with process experts, process owners, QMD and
Finance. Leopad Group’s current Standard Operating Procedures (SOP) will be absorbed
as WBS with relevant changes. This team also will discuss and propose both
digital and manual reporting for Steering Committee approval. Approved WBS will
be tested during AST and UAT.
WBS
brainstorming session on weekends
Many
decision pertaining policies and processes will be made during SDD & AST by
Process Owners and Steering Committee. Therefore, highest commitment and
cooperation required from all team members required during meetings, trainings
and brainstorming sessions. Many thanks for your support and see you next
month.
Lets Make It Happen”
JOURNEY
TOWARDS “GO-LIVE”
by Soman
Dear Team,
We are crossing the half year mark
today for year 2017. As at today, we have travelled 9 months journey of ERP
Implementation process. Data gathering, basic trainings, cross functions and
gap analysis activities have been carried out throughout this period. We will
be entering another important phase which Application Solution Testing (AST)
and User Acceptance Test (UAT). We have many more tasks to be completed before
the AST internally. Deciding the requirements and setting up the basic data
must be done upfront in order to ensure smooth AST. Process owners are required
to conduct more internal discussions and prepare the proposals for Steering
Committee’s review.
Process owners and few key members were only
involved during first half of the implementation process. During second half,
members from all branches, business units and departments will be involved to
test the process flow. More testing sessions will be carried out from July
onwards until “Go- Live” stage. Key personnel from all branches, business units
and departments need to attend this session to test and verify the process
flow. Process owners will conduct trainings for all the key personnel related
to their processes.
Apart from
this, Group ICT department will also closely liaise with branches pertaining
enhancement of ICT infrastructure. They have completed their survey and will
discuss the solutions with branch managements.
As mentioned during the ERP launch
meeting, the entire Leopad Group will be going through a huge transformation
(change management). This transformation will be the main platform to prepare
and Leopad Group in adapting digital economy in the near future and also
achieving Leopad Vision 2022.
The journey
towards digitalized world requires fullest cooperation and commitment from
entire members of Leopad Group. Your continuous support will ensure the
progress to the greater level. On behalf of Steering Committee, I would like to
thank all for your contributions till to date and hoping for the continuous
support until we “Go-Live”.
“Lets Make It Happen”
Subscribe to:
Posts (Atom)
Happy Deepavali
The festival of light is here! May you be the happiest and may love be always with you. Happy Deepavali!
-
We already know that an oil or petroleum refinery is a place where natural, raw oil is processed into refined products like petroleum, g...
-
T he inspection of plant and pipework for CUI can be extremely expensive if all insulation material has to be removed. Often windows a...